
Solar
Utility Solar Array 14
- Industry
- Solar
- Foundation
- PEN — 240 point
- Soil
- Sand mix
The challenge
A 240-point utility array on a tight construction schedule with a single access road.
- 01
Site conditions
Loose sand mix over compacted subgrade, minimal load-bearing without deep footings.
Sand mix
- 02
Engineering approach
Single crew, sequential driving pace matched to panel-mounting crews behind them.
PEN — 240 point
- 03
Installation
Installed in 18 days, 240 points.
Performance
- 18 days
- Install duration
- 2.2×
- Bearing capacity achieved
- 82%
- Concrete saved
- 0 m³
- Soil excavated
Application
Eco ResortBlack Langur Retreat Centre
Kalpetta, Wayanad
- Trees cut
- 0
- Less settlement
- 81%
- Test load carried
- 2.2×
InstitutionalDevagiri Library Book Tower
Kozhikode, Kerala
- Foundation installed
- 1 day
- PEN points
- 5
- Days library closed
- 0
ResidentialHillside Residence
Wayanad, Kerala
- Install duration
- 2 hours
- Bearing capacity achieved
- 2.6×
- Concrete saved
- 80%
