Skip to content
A row of ground-mounted solar panels on a gravel bed

Solar

Utility Solar Array 14

Industry
Solar
Foundation
PEN — 240 point
Soil
Sand mix

The challenge

A 240-point utility array on a tight construction schedule with a single access road.

  1. 01

    Site conditions

    Loose sand mix over compacted subgrade, minimal load-bearing without deep footings.

    Sand mix

  2. 02

    Engineering approach

    Single crew, sequential driving pace matched to panel-mounting crews behind them.

    PEN — 240 point

  3. 03

    Installation

    Installed in 18 days, 240 points.

Performance

18 days
Install duration
2.2×
Bearing capacity achieved
82%
Concrete saved
0 m³
Soil excavated