Utility Solar Array 14

01The challenge

A 240-point utility array on a tight construction schedule with a single access road.

02Site conditions

Loose sand mix over compacted subgrade, minimal load-bearing without deep footings.

Sand mix
SOIL SECTION · SITE-SPECIFIC
PLAN DRAWING · SLEEVE LAYOUT
03Engineering approach

Single crew, sequential driving pace matched to panel-mounting crews behind them.

PEN — 240 point
04Installation

Installed in 18 days, 240 points.

INSTALL · 01
INSTALL · 02
TECHNICAL DRAWING
06Performance
18 days

Install duration

2.2×

Bearing capacity achieved

82%

Concrete saved

0 m³

Soil excavated

07Lessons learned