Skip to content
Devagiri Library book tower lit at night, built on PEN Foundation installed in one day

Institutional · Kozhikode, Kerala

Foundation in 1 day. A library that never closed.

Five PEN points carry a 10 m steel book tower inside the working library of St. Joseph's College, Devagiri. Installed in one day, without breaking its floor.

Foundation installed
1 day
PEN points
5
Book tower, G+2
~10 m
Footing pits dug
0
Days the library closed
0

The library had to stay open. That was the condition before a single line was drawn.

St. Joseph's College (Autonomous), Devagiri, wanted a book tower inside its library: a 10 m, G+2 structure wrapped around a steel spiral stair, lined with shelves, made for students to climb, sit and read in. They also wanted to keep the floor it would stand on.

That floor is vacuum dewatered. The water is drawn out of the concrete while it is fresh, the surface is power floated, and what is left is dense, flat and laid once. Break it and the patch never matches again.

So the foundation had to go in without pits, without a month of curing, and without taking the reading room out of use. It went in in one day.

The constraint

A working library, and a floor that could not be broken

Five steel columns would carry the tower. With conventional isolated footings, that meant five pits cut through the floor, spoil carried out between the shelves, reinforcement and wet concrete on site, and a 21-day cure before anything could stand on them. End to end, 30 to 40 days of a closed, noisy zone in the middle of the library.

The college did not want that. Their architects, Elansa Design Studio, did not want it either. The answer had to come from the foundation.

No footing pits. No curing. No day the library was closed.

The brief, in three lines
PEN Foundation installation inside the working Devagiri library, shelves in place around the workFinished Devagiri book tower with steel spiral stair and shelvingInstallation dayToday
Drag to compare. The same room, the same shelves. Only a narrow strip was opened for the plinth beam.
The PEN solution

Five points, one day

PEN Foundation is a patented, zero-excavation foundation. A precast node sits at ground level and four engineered steel nails are driven through it into the soil at a batter, then grouted. The nails engage a volume of soil much wider than the node, and the point carries load as soon as installation and checks are complete. There is no pit and no curing cycle.

Site investigation at Devagiri found soil bearing capacity above 200 kN/m². With five columns coming down to support the tower, we designed five PEN points, one under each column, set out on the semicircular arc of the stair. Before any cut, the existing slab was scanned with non-destructive testing to locate its reinforcement.

Five foundations. One working day.

Day 1 · Devagiri Library
  1. 01Set outFive points marked on the stair arc
  2. 02ScanNDT scan of the slab for rebar
  3. 03Open stripNarrow cut for the plinth beam only
  4. 04DriveFour nails per node, at a batter
  5. 05Grout and checkNon-shrink grout, quality sign-off
  6. 06Hand overReady for plinth beam and steel
PEN at Devagiri
1 day
Conventional footing
30 to 40 days
  • PEN Foundation installation inside the working Devagiri library, shelves in place around the work
    Installing PEN inside the library
  • Steel spiral stair rising through the plywood shelving of the Devagiri book tower
    Factory steel, bolted on site
  • Students reading on the spiral stair
    The tower in use
The system

A fast foundation needs a structure built for speed

A one-day foundation only helps if the rest of the building is designed to keep up. Devagiri was planned that way from the top down.

  • A light towerSteel frame with plywood shelving. Keeping the superstructure light kept the foundation loads modest.
  • An all-steel spiral stairThe stair turns around its own central shaft column, on its own foundation.
  • Floor ties at every levelThe tower connects to the existing building at each floor. Lateral load leaves at each level, so the moment reaching the base stays small.
  • One plinth beam for the groupA 250 x 450 mm plinth beam ties all five PEN points and the stair shaft foundation together, so six supports act as one. TMT bars welded to each node top lock it into the beam.
  • Factory-made steelAll steel was pre-engineered and fabricated in the factory, then bolted up on site. Columns land on the PEN nodes through anchor bolts.
The result

Built fast, built clean, built around its readers

The library stayed open throughout. The floor around the tower is the floor the college laid. The tower went up on steel made in a factory and bolted to foundations that were ready the day they went in.

In 2024 the project received the SSMB Award for Best Built Steel Structure, competing against a project by a ₹7,000 crore group. The award recognises the whole team: the college, Elansa Design Studio and the steel contractors. PEN is the foundation under it.

The planning of every aspect combined with effective site management enabled swift completion in under a year.

Karan J Fraanc, Elansa Design Studio, in SSMB
For your project

What Devagiri means for you

Design the space. The foundation fits the plan.

  • Five points followed a semicircular arc around a spiral stair
  • No pits, so shelving and finishes around the work stayed in place
  • A light steel and plywood tower, quick to erect
Interior of the Devagiri book tower
The evidence

Why engineers can trust a foundation in one day

Speed is only useful if the numbers behind it hold. Every PEN project is designed for its own soil and loads before a single nail is driven. At Devagiri that meant a site investigation, a full load path from shelf to soil, and a drawing your consultant can check.

  • NABL-accredited labsTested across different soils
  • PLAXISGeotechnical simulation studies
  • ANSYSStructural finite element analysis
  • NDTValidated through non-destructive testing
The bigger picture

A new-generation foundation, and a sustainable one

C-DISC Technologies is reinventing construction from its first point: the foundation. PEN Foundation installs in hours instead of 30 to 40 days, uses 94% less cement and 96% less water than a conventional footing, and cuts carbon by over 1.5 tonnes for every 1,000 sq ft built, while leaving the site largely as it was found.

Devagiri shows what that means when the site is a building people are using. The fastest foundation was also the one with the least hassle.

Questions

Frequently asked

  • Can a foundation really be installed in one day?

    Yes, for suitable low-rise structures. Each PEN point installs in hours. At Devagiri, all five points for a G+2 book tower were installed in one day, with no curing period afterwards.

  • How do you build a foundation inside an existing building without breaking the floor?

    PEN needs no footing pit. Nails are driven from the surface through a precast node. At Devagiri the slab was scanned first, and only a narrow strip was opened for the plinth beam.

  • Is PEN suitable for steel structures?

    Yes. Steel columns bolt to the PEN node through anchor bolts. Devagiri's book tower and spiral stair are both steel.

  • Is PEN a sustainable foundation?

    PEN uses 94% less cement and 96% less water than a conventional footing, avoids excavation, and is GRIHA listed.

  • What testing supports PEN?

    Testing across different soils by NABL-accredited laboratories, PLAXIS and ANSYS simulation studies, and non-destructive testing. Each project is designed for its own soil and loads.

  • Which buildings can use PEN?

    Suitable low-rise construction up to G+2, after a review of soil, loads and site. Taller structures are on the development roadmap.

For engineers

Technical data sheet

The parameters behind the story, for consultants and reviewers who want to check the design.

Project record · Devagiri Book TowerSt. Joseph's College, DevagiriRef: GA14, Rev 00
StructureBook tower with steel spiral stair, G+2, about 10 m
SuperstructurePre-engineered steel frame, plywood shelving
Columns on PEN5 steel columns on a semicircular arc
StairAll-steel spiral on a central shaft column, own foundation
Soil bearing capacityAbove 200 kN/m² (site investigation)
Foundation5 PEN points; precast node with 4 battered galvanised nails, tungsten carbide tipped, grouted
Column connectionFoundation anchor bolts to PEN node
Tie systemPlinth beam 250 x 450 mm, ring and radial, linking PEN group and stair shaft foundation; TMT bars welded to node top
Lateral systemFloor-level ties to existing frame at each storey
Existing floorVacuum dewatered floor retained; NDT scan before cutting; plinth-beam strip only
Installation time1 day for all 5 points; no curing period
SteelFactory fabricated, site erected
PEN validationNABL-accredited lab tests across soils; PLAXIS and ANSYS studies; NDT
RecognitionSSMB Award 2024, Best Built Steel Structure
Section A-A through the book tower showing PEN foundations
Section A-A. Nails shown at batter below ground level.
PEN foundation plan with five nail foundations on the stair arc
PEN foundation plan
PEN foundation section detail with node, plinth beam and anchor bolt
PEN foundation detail

Building inside a site that cannot stop?

Send us your location, drawings and soil data. Our engineers will tell you whether PEN Foundation fits, and what it would take.

Request a Project Assessment