The library had to stay open. That was the condition before a single line was drawn.
St. Joseph's College (Autonomous), Devagiri, wanted a book tower inside its library: a 10 m, G+2 structure wrapped around a steel spiral stair, lined with shelves, made for students to climb, sit and read in. They also wanted to keep the floor it would stand on.
That floor is vacuum dewatered. The water is drawn out of the concrete while it is fresh, the surface is power floated, and what is left is dense, flat and laid once. Break it and the patch never matches again.
So the foundation had to go in without pits, without a month of curing, and without taking the reading room out of use. It went in in one day.
A working library, and a floor that could not be broken
Five steel columns would carry the tower. With conventional isolated footings, that meant five pits cut through the floor, spoil carried out between the shelves, reinforcement and wet concrete on site, and a 21-day cure before anything could stand on them. End to end, 30 to 40 days of a closed, noisy zone in the middle of the library.
The college did not want that. Their architects, Elansa Design Studio, did not want it either. The answer had to come from the foundation.
No footing pits. No curing. No day the library was closed.

Installation dayTodayFive points, one day
PEN Foundation is a patented, zero-excavation foundation. A precast node sits at ground level and four engineered steel nails are driven through it into the soil at a batter, then grouted. The nails engage a volume of soil much wider than the node, and the point carries load as soon as installation and checks are complete. There is no pit and no curing cycle.
Site investigation at Devagiri found soil bearing capacity above 200 kN/m². With five columns coming down to support the tower, we designed five PEN points, one under each column, set out on the semicircular arc of the stair. Before any cut, the existing slab was scanned with non-destructive testing to locate its reinforcement.
Five foundations. One working day.
Day 1 · Devagiri Library- 01Set outFive points marked on the stair arc
- 02ScanNDT scan of the slab for rebar
- 03Open stripNarrow cut for the plinth beam only
- 04DriveFour nails per node, at a batter
- 05Grout and checkNon-shrink grout, quality sign-off
- 06Hand overReady for plinth beam and steel
- PEN at Devagiri
- 1 day
- Conventional footing
- 30 to 40 days

Installing PEN inside the library 
Factory steel, bolted on site 
The tower in use