Eco Resort

Backwater Eco Resort

Industry
Eco Resort
Location
Alappuzha, Kerala
Foundation
PEN — 6 point
Soil
Water-rich alluvial

The challenge

Water-table-adjacent site where conventional footings would have required continuous dewatering.

  1. 01

    Site conditions

    Alluvial soil, high water table, root zones from mature trees the client wanted preserved.

    Water-rich alluvial

  2. 02

    Engineering approach

    PEN nodes set without dewatering; root zones left undisturbed within 1.5 m of each node.

    PEN — 6 point

  3. 03

    Installation

    Installed in 1 day, 6 units.

Performance

1 day
Install duration
2.4×
Bearing capacity achieved
78%
Concrete saved
0 m³
Soil excavated